Additional Images

The Renwick project included the demolition of the existing bins and structures that had been damaged in a storm. New construction started with a 20,000 BPH truck receiving system complete with new truck receiving building. The truck receiving system fed a new 20,000 BPH receiving leg inside a support tower feeding a 20,000 BPH bill fill conveyor with catwalk. The new storage bins included three new Sukup 60' diameter grain bins each with a storage capacity of 266,000 bushels. The bins included a zero entry bin sweeps that fed a 10,000 BPH reclaim drag conveyor that fed back into the receiving leg and into a 5,500-bushel overhead truck loadout bin.